The one principle to remember: the money you've paid must always be less than or equal to the value of work completed The moment you pay ahead of the work, bargaining power moves from you to the contractor
The first milestone must be small — 10–15% is a reasonable deposit. Contractors who ask for 30–40% before starting often use your money to finish old jobs — the start of the abandonment cycle
The final milestone must really exist — The last 10% is paid only after inspection and all fixes. Every house has minor defects after completion; if the money's gone, the tradespeople disappear along with their responsibility
Inspect before every payment — Visit the site yourself or send someone (hiring an engineer at 2,000–5,000 baht per milestone is far cheaper than the damage), photograph everything as evidence, and pay through channels with a record — never pay cash without a receipt
Bhoon Kharn's milestone system does this automatically: set milestones with percentages, the contractor uploads progress photos, the owner approves before paying, and everything has a full history. It's free in the project management system